Shares first place as the best lecturer of KulenDays 20 and PMI Conference 2009 in Zagreb. In addition, he was in TOP 10 lecturers at the MS SINERGY 2009 and MS VISIA 2009, 2010. He was named the best lecturer of WINDAYS 2008 while his lecture was also voted as the best. He is a regular lecturer for Project Management in MS Innovation Center in Varaždin, Logosoft Sarajevo in Bosnia and Herzegovina and SEAVUS GROUP in Skopje Macedonia. Today he works as a business consultant, adn Project Manager in PERPETUUM MOBILE d.o.o. He has got a lot of experience working with people in different business processes and also possesses great knowledge in information technologies and financial services. After completing his college he started working on projects in different business areas (banking, manufacturing, automotive industry, distribution, oil companies, etc.) developing and implementing ERP systems into different companies. Interests: Project Management and MS PROJECT

Now I have this my custom field in the Cost Table: Now I will choose that I want Formula for this field:

I am going to save the plan as a Baseline:

You can see that some of them are over allocated, but this is not relevant for our story! My Blog reader have a problem! He want to know how much money did he spend and, he wants that in percentage of Baseline in MS PROJECT 2010.